Consultation

Have your say

In July 2017 Linkcity held a public consultation for the community to view the proposals for the Luton Street regeneration, which is being delivered in partnership with Westminster City Council as part of the Church Street regeneration area.

The consultation was held on Thursday 27 and Saturday 29 July 2017 at the Penfold Street Community Hub.

If you are not able to attend and would like to view the information displayed at the consultation, please click here.

The deadline for feedback has now passed and the project team are in the process of reviewing all of the comments received from local residents.


Proposals for the Orange Park Car Park on Fisherton Street

On Thursday 28 September 2017 Linkcity held a drop-in session at Poynter House, for local residents to view proposals for three new homes on the car park site next to Orange Park on Fisherton Street.

An invitation letter publicising the drop-in session was sent to 168 households and businesses around the Car Park site on Friday 21 September 2017.


Sketch view showing the proposed massing of the three new homes

Members of the project team were on hand to discuss the proposals and answer questions.

If you were unable to attend and would like to view a copy of the information displayed at the drop-in session on please click here.


Programme

December 2014
Linkcity appointed by Westminster City Council

March 2015
Initial public consultation

July 2017
Second public consultation

Autumn 2017
Submission of Planning Application to Westminster City Council

Spring 2018
Anticipated planning decision

June 2018
Works commence on site, subject to planning approval

August 2020
Luton Street development complete